ADJ were tasked with Resurfacing this busy retail park.
Works included fully resurfacing the car park complete with new thermoplastic markings, minor civil works and landscaping.
Resurfacing a busy retail park.
1 week
3355m2
Asphalt Surfacing External Works
As standard practice from ADJ, we submitted a detailed programme of works with highlighted phasing plan to our client and all effected tenants before any works commenced. We also want to ensure that everyone involved is fully aware of the works and how they can help if necessary. Due to nearby residential properties, this project was carried out during normal working hours.
Works were completed exactly to our programme of works with very minimal disruption. Closing large sections of parking in a retail park is obviously going to cause disruption, but our dedicated traffic management teams ensured visiting customers found alternative parking safely and efficiently.