ADJ Surfacing carry out full site resurface to this North West Retail Park.
Full Site Resurface
Linear Drainage Replacement
Line marking
Island Installation
2 Weeks
7545m2
Surfacing
Drainage
Line Marking
External Works
We were tasked to phase this car park and resurface it in its entirety. This required our Operational Team to strategically propose a plan to get this retail park resurfaced, causing minimal disruption to the retailers on site.
Due to the size of the car park and it having 2 exits, we phased the main car park over 3 sections during the day and resurfaced the route infront of the stores out of hours. We also replaced 50lm of defected drainage channels due them being very unsafe and not in working order. Each phase was closed using heras fencing, ensuring maximum safety for both ADJ Staff and the general public. Our dedicated traffic management operatives ensured vehicles were guided to available parking when required.
A great outcome and after returning to site numerous times, this car park will still be there for years to come.