Major refurbishment works to prime Yorkshire Industrial Facility.
Break out 200m2 Concrete
Install new Sub-surface Asphalt
Install new Surface Course
Install new Lining layout
1 week
200m2 Concrete
1850m2 Asphalt
Excavation Works
Asphalt Surfacing
Line Markings
We were instructed to survey this Industrial Estate on behalf of Workman LLP and propose our recommendations for the repairs of the main carriageway through site. Following our visit we proposed to break out a heavily defected area of concrete and replace with asphalt and resurface the central carriageway.
During the week we fenced off the isolated concrete area allowing the facility to continue to operate. We disposed of the concrete off site and installed a new type 1 Sub Base. Again, during the week we installed the new road base and binder course asphalt whilst isolated from the general usage of the site. We then returned Sunday whilst the site was closed to complete the major carriageway and line markings.